Implementation Milestones

1999-May 2000

  • CAO Benchmarking Project begins with a small workgroup that includes staff from the Regions of York, Niagara, Waterloo and Peel as well as the Cities of Toronto and London.

  • Initial discussions lead to a consensus that while the work ahead is complicated, the benefits can be very high.

  • Information sharing and networking are the two early benefits as colleagues interact and discuss performance data.

  • Early attempts at performance data comparison met with limited success.

  • A more formal project management framework is created with York taking the lead. Ontario Ministry of Municipal Affairs and Housing supports the project with funding and staff participation.

  • Expert Panels are created to study roads, solid waste, emergency medical services (ambulance), water and wastewater services, long

  • term care and internal support services.

May-July 2000

  • Small workgroup meets to review data collected and broad accomplishments to date, and to redefine the project management framework for the project.

  • A more focused strategy emerged and development of project charter and workplan completed.